A study on Scheduling of Human Resource Constrained Projects with A Single Model of Minimised Duration Targets
DOI:
https://doi.org/10.54097/j5zb5f65Keywords:
Minimising duration, Human resource constrained project scheduling, Integer planningAbstract
This paper investigates the project scheduling problem with single-mode human resource constraints under the minimised duration target. In civil engineering construction projects, human resource is one of the key factors that constrain the duration. In this paper, an integer planning model considering human resource constraints is constructed with the aim of minimising the project duration by optimising the allocation and scheduling of human resources. By introducing an efficient solution algorithm - CPLEX optimisation technique, this paper successfully solves this complex problem and provides real cases to verify the effectiveness of the model and algorithm. The results show that a reasonable human resource scheduling strategy can significantly shorten the project duration and improve the efficiency of project management under resource-constrained conditions.
Downloads
References
[1] Liu Shixin, Wang Mengguang, Tang Jiafu. A genetic algorithm for solving resource-constrained engineering scheduling problems. Journal of Systems Engineering, 2002, 17(1): 1-7.
[2] Qi Donghai, Song Xiangqun. Engineering Project Schedule Management. First Edition. Liaoning: Dalian University of Technology Press, 2001.135-143.
[3] Liu, Z. Y.. Resource-constrained engineering scheduling and its application to engineering supply chain design: [PhD thesis]. Library of Huazhong University of Science and Technology, 2005.
[4] Zhou M., Sun Shudong. Principles and Applications of Genetic Algorithms. First Edition. Beijing: National Defence Industry Press, 1999.78-80.
[5] Haga Wayne A., Marold Kathryn A. A Simulation Approach to the PERT/CPM Time-Cost Trade-Off Problem. Project Management Journal, 2004, 35(2): 31-37.
[6] John Moussourakis, Cengiz Haksever. Flexible Model for Time/Cost Tradeoff Problem. Journal of Construction Engineering & Management, 2004, 130(3): 307-314.
[7] Vanhoucke Mario. new computational results for the discrete time/cost trade-off problem with time-switch constraints. European Journal of Operational Research, 2005, 165(2): 359-374.
[8] Chassiakos Athanasios P., Sakellaropoulos Serafim P. Time-Cost Optimization of Construction Projects with Generalized Activity Constraints. Journal of Construction Engineering & Management, 2005, 131(10): 1115-1124.
[9] MU Jingbo, HOU Jingfeng, WANG Liang, LIAO Weizhang. Building construction organisation and management [M]. Beijing: Tsinghua University Press, 2013:35.
[10] Choi Jaein, Realff Matthew J., Lee Jay H. Dynamic programming in a heuristically confined state space: a stochastic resource-constrained project scheduling application. Computers & Chemical Engineering, 2004, 28(6/7): 1039-1058.
[11] Vicente Valls, Francisco Ballestin, Sacramento Quintanilla. A Population-Based Approach to the Resource-Constrained Project Scheduling Problem. Annals of Operations Research, Basel, 2004, 131(1-4): 305-324.
[12] Bonnal Pierre, Gourc Didier, Hameri Ari-Pekka et al. A linear-discrete scheduling model for the resource-constrained project scheduling problem. Construction Management & Economics, 2005, 23(8): 797-814.
Downloads
Published
Issue
Section
License

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.